PROTOCOL OF THE WORKING
GROUP MEETING for Establishing an
International Consortium for Through Train Traffic Rehabilitation on the
Veseloe-Ingiri Section
The
meeting of the Working Group for establishing an international consortium for
through train traffic rehabilitation on the Veseloe-Ingiri section was attended
by representatives of the Armenian side, Georgian side, Abkhazian side, Russian
side. A list of the meeting participants is enclosed (Annex 1).
The
meeting participants informed each other on representatives to the Working
Group from the
The
following agenda was agreed at the Working Group meeting:
1. Principles
of establishing the international consortium;
2. Organizational
and legal form of the international consortium;
3. Development
of a business plan for the international consortium;
4. Long-term
perspectives for developing railway connections in the Transcaucasus region;
5. Next
meeting of the Working Group.
Having
considered the items of the agenda, the sides
decide as follows:
Concerning
Agenda Item 1:
1. The
sides agree that the working name of the International Consortium shall be the
‘Black Sea Railway Consortium’.
2.
The main objective of the International Consortium (hereinafter Company) is to
organize rehabilitation and further operation of infrastructure on the
Veseloe-Ingiri section.
Transfer
of railway infrastructure on the Veseloe-Ingiri section to the joint stock
company is a necessary precondition for successful project implementation. The
infrastructure transfer shall be provisioned by a separate agreement. The Company
shall receive investment return guarantees for the project implementation.
3. The
project funding shall be provided by the Company.
4. The
sides agree to give the functions of the Working Group Secretariat to the
Department of Foreign Relations of the joint-stock company.
Concerning
Agenda Item 2:
1. The
sides agree that the International consortium shall have the form of a
joint-stock company.
2. The
initial capital will be shared by the Company founders.
3. The
sides agree to consider Company’s constituent instruments prepared by Russian
Railways JSC (Annex 3 and 4), and to forward their comments and proposals concerning
these documents to the Working Group Secretariat by June 1 2006 to be agreed at
the next regular Working Group meeting.
Concerning
Agenda Item 3:
The
sides agree that the Company shall cover costs for involving a consultant to
develop the Company’s business plan, if necessary.
Concerning
Agenda Item 4:
The
sides agree to prepare proposals for mutual freight transportations by railway
in the
Concerning
Agenda Item 5:
As
proposed by the Georgian side, the next regular Working Group meeting shall be
held in
This
protocol was signed by May 4 2006 in
On
behalf of the Armenian Railways À. V. Khrimyan
On
behalf of the
On
behalf of the Abkhazian Railway Section A. Y. Turukin
On
behalf of the Russian Railways M. P. Akulov